Canal and Drainage Act, 1873 › OF THE CONSTRUCTION AND MAINTENANCE OF WORKS

Section 20 Canal and Drainage Act, 1873 — Supply of water through intervening water-courses or change of source of water supply

(1) Whenever an application is made to a Divisional Canal Officer for the supply of water from a canal through an existing or a new water-course or change of source for water supply of any land, the Divisional Canal Officer, if considers it appropriate, shall–

(a)  give public notice to all persons interested and personal notice to the land-owners through whose land a link water-course is to pass, to show cause on a day not less than fourteen days from the date of such notice why the said supply should not be so conveyed, or the source of supply be changed;

(b)  after making a public enquiry, the Divisional Canal Officer shall determine, whether and on what conditions the said supply shall be conveyed through such water-course or that the source of water supply shall be changed or the link water-course shall be aligned and constructed; and

(c)  subject to policy instructions of the Provincial Government, pass such order as he deems fit.

(2)  The Divisional Canal Officer shall, within fifteen days of passing the order, send the record of the case to the Superintending Canal Officer for further proceedings.

(3)  A person aggrieved by the order passed under sub-section (1) may file objections with the Superintending Canal Officer within thirty days of the passing of such order.

(4)  The Superintending Canal Officer, at his own or on the objections, shall pass such order as he deems fit within ninety days from the receipt of the record or receiving of the objections.

(5)  In case no objections are filed and the Superintending Canal Officer fails to pass an order within ninety days, the order of the Divisional Canal Officer shall be deemed to have been confirmed and the record shall be sent back to the Divisional Canal Officer.

(6)  The order passed or confirmed under this section shall be final and binding on the applicant, the persons responsible for the maintenance of the said water-course, all the persons affected by the change of source of water supply and the land-owners through whose land the link water-course shall pass.

(7)  The applicant shall not be entitled to use the said water-course until he has paid the expenses of alteration of such water-course necessary in order to his being supplied through it, and also such share of the first cost of such water-course as the Divisional or Superintending Canal Officer may determine.

(8)  The applicant shall not be entitled to use the link-water-course, until–

(a)  he has paid to the land-owner the compensation for the land occupied by such link water-course in whatever shape if it is determined through mutual agreement; or

(b)  possession of land for the said link water-course has been acquired under the provisions of this Act.

(9)  The applicant shall also be liable for his share of cost of maintenance of the water-course as long as he uses it.]

‹ Section 19 — Adjustment of claims between persons jointly using water-course | Section 20-A — Special powers of Divisional Canal Officer to initiate cases under section 20 ›