Canal and Drainage Act, 1873 › OF DRAINAGE

Section 59-A Canal and Drainage Act, 1873 — Prohibition and control regarding the discharge of effluent into canal and drainage works

(1) The Provincial Government may, by notification in the official gazette, prohibit the discharge of any effluent, including any solid or liquid matter or combination of them from industrial, municipal or any other source, into any river, canal and drainage work including any natural drainage channel.

(2)  In case of contravention of sub-section (1), the Divisional Canal Officer, after such enquiry including taking of sample, may impose such special drainage charges as may be prescribed and shall take other necessary steps to prevent such contravention and consequential cost so incurred shall also be recoverable from the person found responsible for such contravention.

(3)  After the publication of notification under sub-section (1), any person, organization or entity, interested in discharging such effluent into any river or drainage work, including any natural drainage channel, shall apply to the Divisional Canal Officer or any other person authorized by the Provincial Government in this behalf, for grant of permission for the discharge of such effluent.

(4)  The applicant shall obtain a certificate of no adverse impact of such discharge on environment from the authority designated in this behalf under any law for the time being in force relating to environment.

(5)  The Divisional Canal Officer or the person authorized under sub-section (3), shall, after giving an opportunity of hearing to the applicant and such further inquiry as he deems necessary, determine the feasibility of such permission on the basis of the certificate mentioned in sub-section (4), capacity and flow condition of the channel and may either refuse or grant permission subject to such terms and conditions including levy of drainage charges as may be prescribed.

(6)  Any person aggrieved by the order passed by the Divisional Canal Officer under this section may file an appeal before the Chief Engineer within ninety days of the passing of the order.

(7)  The Chief Engineer may, on an appeal or at his own, confirm, modify or set aside the order of the Divisional Canal Officer.]