Punjab Irrigation, Drainage and Rivers Act, 2023 › RIVERS, EMBANKMENT WORKS AND FLOOD CONTROL
Section 96 Punjab Irrigation, Drainage and Rivers Act, 2023 — Flood forecasting and routing analysis
(1) The Government shall maintain an adequately resourced unit to undertake, among other things, the following tasks, namely:
(a) continuously collect, record and analyze relevant information on meteorological conditions, observed patterns of rain fall and melting of glaciers and snow in their watershed, and other related phenomena and develop a forecast of expected flows in various rivers in the Punjab as well as to further enhance any similar forecast received through other authorities and sources;
(b) identify areas that are likely to be inundated by such flows;
(c) identify any dam, headwork, weir, bridge, canal, drain, embankment or other irrigation work that is likely to become unsafe or vulnerable in view of the water levels achieved or likely to be achieved under such flows;
(d) identify areas that are likely to be inundated if the water leaks or escapes from a dam, headwork, weir, canal, drain, embankment or other irrigation work, and the route such water is likely to take before draining off completely; and
(e) promptly disseminate information on the above aspects as required under a relevant Standing Instruction.
(2) The unit shall consist of a head and other officers and staff of such description and in such number as the Government may, from time to time, fix.
(3) The said head, officers and staff shall be appointed in such manner and perform such duties and exercise such powers as may be prescribed.