Pakistan Petroleum (Refining, Blending and Marketing) Rules, 1971
Section 44 Pakistan Petroleum (Refining, Blending and Marketing) Rules, 1971 — Penalty for breach of rules
Any person who contravenes the provisions of any of these rules shall, without prejudice to any other action that may be taken under these rules in relation to the contravention, be punishable for every breach with imprisonment or a term which may extend to three years, or with fine (which shall not be less than fifteen thousand rupees) or with both.
-: 11 :-
SCHEDULE I
[See rule 4, 17 and 27 (1)]
FORM I
FORMAT FOR OIL REFINERY, BLENDING PLANT "(RECLAMATION PLANT)" MARKETING COMPANY FEASIBILITY STUDY
Note 1.- The feasibility report should be prepared by a reputable firm of consultants or such persons who possess technical qualifications as well as experience in oil refining. In the case of blending (reclamation) or marketing projects, this may not be necessary. Paragraphs should be numbered to correspond with those in this questionnaire.
Note 2.- Where the application relates to a particular project e.g. refinery marketing company (blending plant or reclamation plant), then the appropriate information may be furnished.
Note 3.- Name/names of the firm/firms of consultants or the technical personnel/ personnel's responsible for preparing the feasibility report of oil refinery. In respect of blending plant (reclamation plant) or marketing facilities, names technical personnel/personnel's.
Note 4.- The feasibility study should include the information asked for below:-
CHAPTER 1
GENERAL CONSIDERATIONS
1.1. Name and address of the applicant giving details of his commercial interest etc; and past experience in oil industry, if any.
1.2. Capital structure of the proposed company. (No managing agency arrangements should be made).
1.3. Give an approximate indication of the time required to complete the project indicating phasing of work.
1.4. Indicate how the project will be managed. Also indicate if you will be advised by foreign technical consultants.
1.5. Indicate requirements of technical personnel and their availability, and submit an organogram of the proposed organization.
-: 12 :-
CHAPTER 2 MARKET CONSIDERATIONS 2.1. Give estimates of consumption of all petroleum products including base oils and asphalt for internal as well as export. If the product/products are to be locally consumed indicate present local demand of such products and their production and areas of consumption. Also give the local demand and supply position for subsequent years including the year when the projects is expected to materialize. 2.2. Indicate whether product/products are to be locally consumed or exported. Also indicate disposal of the surplus products. 2.3. If product/products are to be exported, indicate potential export areas and give reasons why exports from Pakistan of such product/products would be preferred. This includes supplies to international concerns, airlines, etc. 2.4. Give estimates of production/sales pattern of the company. 2.5. Phased program, e.g. quantities to be marketed and distribution alongwith sources of supply.
CHAPTER 3 LOCATION 3.1. Location of the new industry/installation. 3.2. Availability of utilities (electricity, water, fuel, etc) at the proposed location. Also indicate the stand-by arrangements. 3.3. Availability of raw materials or products at the proposed location. 3.4. Availability of means of disposal of product/products at the proposed location. 3.5. Availability of means of disposal of waste products at the proposed location. 3.6. Availability of terminal depots and other points/of storage.
-: 13 :-
CHAPTER 4
DESCRIPTION OF THE PROPOSED PROJECT
4.1. Describe in detail the proposed project and the manufacturing process and give requirements of materials, utilities and other services. Indicate what arrangements are made or are planned to obtain the materials, utilities and other services.
4.2. Indicate in detail the charge and yields of all the units. Indicate also if the refinery units and ancillaries are designed to yield a maximum production of middle distillates.
4.3. Indicate whether the designed capacity of the refinery units have the flexibility to process heavier crudes with high content of sulphur and salt.
4.4. Describe in detail the transportation arrangements of crude oil/base oil/finished petroleum products.
4.5. Indicate the product mix of the refinery assuming that motor spirit 90 RON,JP-1,JP4,SK,HSD,LDO, base oils and furnace oil would be produced. These products would conform to the specifications currently in force in Pakistan.
4.6. Indicate measures for prevention of air pollution.
4.7. Indicate the cooling arrangements contemplated in the design keeping in view the availability of water in the area. Also indicate if air-cooling will be provided.
CHAPTER 5
USE OF PIPELINES
5.1. If pipeline is used for transportation of crude oil, the following information may be furnished:-
(a) Pipelines
Local
Foreign
Total
Cost of pipeline Land Laying of pipeline Pump stations Civil and Erection cost Cathodic protection Pre-operating expenditure Contingency
-: 14 :-
(b) Spares
(c) Working Capital
Total investment
5.2. Indicate if the pipeline will also be available to other companies designated by the Government at terms acceptable to the parties concerned and approved by the Government.
CHAPTER 6
ESTIMATED COST OF PROJECT AND PROPOSED MEANS OF FINANCING
6.1. Give an estimate of the cost of the project as follows:-
(a) Plant Cost
Local
Foreign
Total
Building Equipment and material Erection Engineering Other Items (Please specify) Total plant erected cost
(b) Spares etc
Spare Parts. Miscellaneous items. Start-up expenses Total :
(c) Working Capital :
(d) Total Investment
6.2. How is the cost of project given above proposed to be met. Please define mode of financing of project and the capital structure of the company. Give financial justification of the project.
-: 15 :-
CHAPTER 7
ECONOMICS OF THE PROJECT
7.1. Give detailed estimates of the estimated profitability of the venture. Following basis is to be used for estimating the profit:-
Local
Foreign
Total
Estimated sales (give details and show basis of pricing used).
Less material cost (give details and show basis of pricing used).
Less operating cost (give details and show basis used).
Gross Profit :-
Less Provision for taxes.
Net Profit
This projection should be for a period of 5 years.
*Detail case for any tax holiday asked by the industry.
7.2. Please include the latest rates for all items including duties and taxes as currently in force. For purposes of study do not ignore payment of duties and taxes.
CHAPTER 8
MISCELLANEOUS
8.1. The extent of Pakistani participation in the project should be clearly indicated for the various phases viz. designing, engineering, fabrication, construction, maintenance, etc. Pakistan personnel should be associated in all the phases and their extent of participation both in number and money-wise should be clearly indicated.
8.2. Indicate details of any foreign exchange savings.
8.3. Indicate the requirements of Pakistani and expatriate technical personnel with a detailed organization.
8.4. Any other relevant information.
-: 16 :-
SCHEDULE II SCHEDULE OF PETROLEUM PRODUCTS
1. Aviation Gasoline 73 Octane 2. Aviation Gasoline 100/130 Octane 3. Aviation Gasoline 115/145 Octane 4. Aviation Turbine Fuel JP-4 5. Aviation Turbine Fuel JP-1 6. High Octane Blending Component 7. Motor Spirit 8. Naphtha 9. Vaporizing Oil 10. Superior Kerosene 11. Inferior Kerosene 12. High Speed Diesel Oil 13. Light Diesel Oil 14. Jute Batching Oil 15. Furnace Oil 16. Lubricating Oils including base Oils 17. White oils 18. Asphalt/Bitumen 19. Greases 20. Mineral Turpentine 21. Solvent Oils
-: 17 : —
SCHEDULE I
FORM 1-A
(See rule 17)
FORMAT FOR SUBMISSION OF APPLICATION FOR REGISTRATION OF BLENDING PLANT, GREASE PLANT, RECLAMATION PLANT AND
WHITE OILS PRODUCTION PLANT
i. Name of the company
ii. Address of the company
iii. List of Directors of the company
iv. Location of the plant
v. Design and capacity of the plant (metric tons per annum).
vi. Confirmation that laboratory facility to check and monitor quality of the products has been established for conducting all requisite tests in accordance with the approved specifications.
vii. Confirmation that all excise bond formalities required under the relevant rules have been completed with the respective Collectorate of Excise and Customs (documentary) proof to be attached).
-: 18 :-
FORM 1-B
( See Rule 16 )
MINIMUM REQUIREMENT FOR SETTING UP OF BLENDING, RECLAMATION AND GREASE PLANTS
BLENDING PLANT Minimum capacity 7500 M.Tons per annum Minimum two blending kettles of capacity of 15 tons each alongwith all necessary facilities.
RECLAMATION PLANT Minimum capacity 1000 M.Tons per annum Blending kettle minimum 10 tons capacity, alongwith all necessary facilities.
GREASE PLANT Minimum capacity 1000 tons per annum Grease blending kettle of 10 tons capacity alongwith all necessary facilities.
Base Oil storage tanks to cover minimum 15 days requirement. Finished products storage tanks to cover 7 days requirement.
Boiler 150 PSI Furnace Oil Storage Tanks. Bulk, Drum and Tin filling machine arrangements.
Dehydration, Acid treating, Neutralization, settling kettles and Vacuum Distillation Unit.
OR An Internationally renowned processing facility fully capable to reclaim lube oil. Base Oil/Reclaimed Oil storage tanks to cover 7 days requirement. Finished products/Reclaimed Oil/Waste Oil storage tanks to cover 7 days requirement. Boiler 150 PSI Furnace Oil Storage Tanks. Bulk, Drum and Tin filling machine arrangements.
Base Oil storage to cover 7 days requirement. Finished products storage to cover 7 days requirements.
Boiler 150 PSI Furnace Oil Storage Tanks Bulk, Drum and Tin filling machine arrangements
-
Filer
-
Labs apparatus for quality Labs apparatus for quality Labs apparatus for quality
Control as under:-
Control as under:-
Control as under:-
i) Kinematic Viscosity bath. ii) Pour Point apparatus. iii) Flash Point apparatus. iv) Centrifuge. v) Furnace. vi) Oven. vii) ASTM D 1500 Colour
meter. viii) Silver sun high shear
mixer. ix) Potentiometer for T N
testing. x) Misc. items test tubes,
balance, glassware etc.
i) Kinematic Viscosity bath. ii) Pour Point apparatus. iii) Flash Point apparatus. iv) Centrifuge. v) Furnace. vi) Oven. vii) ASTM D 1500 Colour
meter. viii) Misc. items test tubes,
balance, glasswares etc. ix) Silver sun high shear
mixer. x) Potentiometer for T N
testing.
Stability test apparatus.
Dropping point apparatus.
Corrison test apparatus
Flash Point apparatus.
Penetrometer. Grease worker Hot Plate Oil separator Hydrometer Balance Oven